ERCOT supports energy plan for the Texas Valley
By Anayancy Ulloa
August 29, 2022
The
McAllen Economic Development Corporation
(MEDC) and American Electric Power
(AEP) held a meeting with Kip Fox, president of Electric Transmission Texas (ETT), in order to publicize the
network expansion and improvement project transmission line serving the Rio
Grande Valley.
AEP
and South Texas Electric Cooperative are transmission service providers for
this estimated $1.28 billion project. The cost would be shared by the 26
million customers of the Electric
Reliability Council of Texas (ERCOT).
During
the meeting, held on August 10, the economic development corporations of
McAllen, Edinburg, Mission and Pharr, in Texas, were summoned, to whom this
initiative was reported in order to work directly with them on any project they
have.
In
an interview, Susie Flores, director of new business recruitment for the US at
MEDC, commented that what is planned is to implement the necessary
infrastructure that allows the placement of new towers, antennas and wiring to
connect high-voltage poles. This plan will make electric transmission service
much more reliable.
“MEDC is currently working
with a company that will install a solar farm and an additional green hydrogen
project, but they are looking for properties where they could install them,” she explained.
One
of the conditions for choosing the property is that it must be close to these
high voltage connections to put your solar farm. Flores mentioned that this is
a project that is contemplated to start up in a period of two to five years.
"At
the moment, if there is a project in any of the economic development
corporations in the region, they will be able to support the installation of
the wiring," she assured.
She
added that there are lines that only support a certain amount of voltage and
with the new lines that will be installed, the capacity to receive and send
energy to the solar farms will be expanded.
PROJECT FEATURES
The Tier 1 plan for the
Lower Rio Grande Valley system improvement project, submitted to ERCOT by American Electric
Power (AEP), calls for the construction of three new substations and the
installation of approximately 352 miles of dual-circuit transmission lines. 345
kilovolts (kV) connecting them.
The
Lower
Rio Grande Valley relies heavily on three main 345 kV long-distance
transmission lines that connect the region to the rest of the state's grid,
although two of the lines, which run parallel to the coast from near Corpus
Christi to the Valley, are susceptible to damage from tropical storms and
hurricanes, according to ERCOT.
Existing
conventional generation capacity is limited and no additional conventional
generation is planned, ERCOT noted
in its report on the project.
Conventional
generation refers to power plants fueled by natural gas or coal, for example,
as opposed to renewable energy such as wind or solar generation.
"Historically,
the LRGV area has experienced reliability challenges, especially during
transmission and generation outages, including those associated with extreme
weather events, to serve existing and projected electricity demand
growth," ERCOT said.
Electricity
demand at the LRGV "load center"
is expected to increase, while the potential for high-use industrial customers
to move into the area is another reason transmission service needs to be
improved, according to the report, which noted that peak summer demand is
expected to reach 3,200 and 3,300 megawatts (MW) by 2027 and 2030,
respectively.
One
MW, which is equal to one million watts, is roughly the amount of energy needed
to power 400 to 900 homes per year.
According
to ERCOT, reliability issues will
arise even without outages of 3,200 MW or more, meaning system upgrades will
need to be in place by 2027. It is important to consider high-impact
weather-related transmission or generation outages and stability and reliability
issues.
According
to ERCOT, the large volume of
renewable resources (wind and solar farms) that have been built in and around
the Lower Valley in recent years limits the ability to import and export
energy, affecting long-term energy transfer. distance between the Lower Valley
and the rest of the ERCOT network. Wind and solar generation capacity in the
Lower Valley was expected to reach approximately seven gigawatts by the end of
2021. One gigawatt equals 1 billion watts.
In
addition to enhancing reliability and stability and optimizing system
resiliency under high-impact weather conditions and increasing the ability to
move power in and out of the area, the enhancements "will provide greater
operational flexibility during planned maintenance outage conditions."
", according to ERCOT.
MORE INFORMATION
McAllen
Economic Development Corporation
6401
S. 33rd Street McAllen, Texas 78503
(956)
682 - 2875
(956)
682-3077